littlerich wrote:Let's say by miracles of miracles it's December 31st 2010. That's 18 months from now. 18 months to build a stadium. Is that actually possible, if they started tomorrow? Anyone? By this i mean not a "record breakers" program possibility but an ordinary building project and everything else that comes along with it (delays, etc...) kinda project.
It's just NOT going to happen so why does he continue to say that it will? He's making a rod for his own back (originally in a Guardian interview he said that the first game of 2009 would be in a new stadium). If i was a Salford fan, i'd be spitting chips and i know what it feels like - i've been there, done that with our East Stand and it still aint frikkin' built.
A 62 week build has been quoted many times , I have poured scorn on that many times
On a prepared level site with access roads already in and no delays you could just,only just build a stadium in 62 weeks
At barton as it is at present you would do well to get anything built in 2 - 21/2 years
Not having a pop , just the way it is people